Is it possible to input task durations in weeks or months ?

It is possible to input task durations in days, weeks or months. Ideally it is better to input these durations in days but if your planning does not allow such precision level you can input them in weeks or in months.

Next to any duration there is a letter “d” which means “days”. If you double click on it you will change it to “w” (weeks) or “m” (months).

Did you find a solution to your question ?
Link to the contact form
Back to the top of the page